Phase 1
Revised Phase 1: Flood Risk Reduction Construction
Proposed March 2023
Dredging, Placement, Stabilization:
-
City Park Lake (includes under I-10)
-
Erie Lake
-
Containment area in University Lake
Improved weir at Stanford Ave

Revised Phase 1: May Street
May Street Improvements:
-
Earthwork
-
Road realignment
-
New bridge (weir removed)
-
Improved E. Lakeshore & Dalrymple intersections
-
Bike/ped paths
-
Lighting
-
Seeding

Potential $2M cost reduction alternative includes re-sizing the “cut” between lakes to reduce span of bridge.
Phase 1: Interim Landscape
Includes:
-
Soil amendment
-
Successional plantings

Phase 1 Construction Budget
-
Flood Risk Reduction Construction $17,874,132*
-
May Street Improvements $11,000,000
-
Interim Landscape $2,500,000
-
Construction Administration $800,000
TOTAL PHASE 1 CONSTRUCTION COST = $32,174,132
TOTAL AVAILABLE PHASE 1 CONSTRUCTION = $32,960,000
* Does not include Campus Lake or College Lake
Phase 1 Schedule
-
Advance Work Project | June-August 2022
-
USACE Permit Application | Submitted September 28, 2022
-
100% FRRD Design | Submitted October 2022 - Revised to include area under existing I-10 bridge | January 6, 2023
-
ULLLC approves FRRD Design | January 12, 2023
-
Phase 1 GMP Proposal Submitted | February 6, 2023
-
Revised GMP Proposal Submitted | February 20, 2022
-
FRR Construction Mobilization Begins | Pending USACE permit approval
-
Interim Landscape Bid Package | June/July 2023
-
May Street Bid Package | Winter 2023/2024
-
FRR Construction Duration: Approx. 12 months