top of page

Project Timeline

Tasks included in Phase One of the work entail due diligence and design followed by project implementation through the Construction Manager At-Risk (CMAR) process.

  • Advance Work Project | June-August 2022

​

  • USACE Permit Application | Submitted September 28, 2022

​

  • 100% FRRD Design | Submitted October 2022  - Revised to include area under existing I-10 bridge | January 6, 2023​

​

  • ULLLC approves FRRD Design | January 12, 2023  

​

  • Phase 1 GMP Proposal Submitted | February 6, 2023

 

  • Revised GMP Proposal Submitted | February 20, 2022 

​​

  • FRR Construction Mobilization Begins | Pending USACE permit approval

             

  • Interim Landscape Bid Package | June/July 2023 

​​

  • May Street Bid Package | Winter 2023/2024 

​​

  • FRR Construction Duration: Approx. 12 months 

Public meetings and opportunities for feedback and engagement occurred throughout 2021. The initial nine-month design process, led by Sasaki, included:

  • Chapter 1 – Listening and Learning: The project team engaged with project stakeholders and the public to identify issues and to hear concerns and ideas.

​

  • Chapter 2 – Design Dreaming: The project team again engaged with the public and stakeholders to prioritize wants and needs, and to begin refining designs set forth in the 2016 Master Plan. The result: “15% design” drawings.

​

  • Chapter 3 – Plan Detail: In-depth review and refinement of the draft schematic design occurred to assure the feasibility of the designs. The result: “30% design” drawings.

Following Schematic Design, the Master Designer in coordination with the Construction Manager At Risk (CMAR) refined the 30% design through 60%, 90% and finally 100% construction document and specification sets.

​

Construction began on Phase 1 of the University Lakes Project in Summer 2022.

bottom of page