Future Phases

All future phases are contingent upon future funding.

Future Phasing Strategy

Corporation Canal

FEMA Flood Mitigation Assistance Grant Award: $14.6M – anticipate Notice of Availability by Sept 2025

Map of Bromley Diversion and Coronation Canal Retrofit.

Priorities for Full Build Out

Plan for Wampold Park improvements and dedicated paths.
SHARED USE PATHS
ESTIMATED COST
Stanford SUP: S. Lakeshore to E. Lakeshore
$881,013
Dalrymple SUP: E. Lakeshore to W. Lakeshore
$5,460,050
W. Lakeshore SUP: Stanford to S. Campus
$2,604,007
Stanford SUP: Wampold Park Connector
$1,104,054
E. Lakeshore SUP: May St. to Stanford
$6,123,598
E. Lakeshore SUP: May St. to Dalrymple
$5,658,557
W. Lakeshore SUP: Dalrymple to S. Campus (paths currently exist)
$5,176,788
TOTAL COST FOR PATHS
$27,008,068
  • $1M in state surplus funding available to address the Stanford SUP from S. Lakeshore to E. Lakeshore.

  • $5M in capital outlay Priority 5 will be used for priority shared use paths, if moved up to P1 in 2027.

  • Philanthropic funds being sought for Milford Wampold Park improvements.