Revised Phase 1: Flood Risk Reduction Construction​

Proposed March 2023

Dredging, Placement, Stabilization:​

  • City Park Lake (includes under I-10)​

  • Erie Lake​

  • Containment area in University Lake

Improved weir at Stanford Ave

Slide4.jpg

Revised Phase 1: May Street

May Street Improvements:​

  • Earthwork​

  • Road realignment​

  • New bridge (weir removed)​

  • Improved E. Lakeshore & Dalrymple intersections​

  • Bike/ped paths​

  • Lighting​

  • Seeding

Potential $2M cost reduction alternative includes re-sizing the “cut” between lakes to reduce span of bridge.

Phase 1: Interim Landscape

Includes:​

  • Soil amendment​

  • Successional plantings

Phase 1 Construction Budget

  • Flood Risk Reduction Construction $17,874,132*​

  • May Street Improvements $11,000,000​

  • Interim Landscape $2,500,000​

  • Construction Administration $800,000

TOTAL PHASE 1 CONSTRUCTION COST = $32,174,132​

TOTAL AVAILABLE PHASE 1 CONSTRUCTION = $32,960,000​

* Does not include Campus Lake or College Lake

Phase 1 Schedule

  • Advance Work Project | June-August 2022

  • USACE Permit Application | Submitted September 28, 2022

  • 100% FRRD Design | Submitted October 2022  - Revised to include area under existing I-10 bridge | January 6, 2023

  • ULLLC approves FRRD Design | January 12, 2023  

  • Phase 1 GMP Proposal Submitted | February 6, 2023 

  • Revised GMP Proposal Submitted | February 20, 2022 

  • FRR Construction Mobilization Begins | Pending USACE permit approval              

  • Interim Landscape Bid Package | June/July 2023 

  • May Street Bid Package | Winter 2023/2024 

  • FRR Construction Duration: Approx. 12 months 