top of page

The University Lakes Restoration Project team reminds the public that May Street is closed to all traffic between Dalrymple Drive and East Lakeshore Drive.
This applies to vehicles, cyclists, and pedestrians.

Pelicans visit the University Lakes

REIMAGINE THE
LAKES

Exciting changes are coming to

the University Lakes System.

A partnership between LSU and

state and local partners is working

to create a more sustainable lakes system through ambitious environmental restoration that will also add tremendous recreational value for all people of Baton Rouge.

What's Happening at the Lakes?

Phase 1

The May Street bridge deck was recently poured and infrastructure continues to go in in preparation for paving the new street. The new parking lot at May Street is also taking shape as curbs are installed. Currently, May Street is on track to reopen early this winter!

​

Around City Park Lake and Lake Erie, many of the planted native species are in bloom! Landscape maintenance is ongoing to remove weeds and cut back new growth periodically in the newly landscaped areas. Landscape contractor Rotolo Consultants, Inc. (RCI) was recently retained to continue maintaining the new shoreline landscapes through October 2027.

Recent drone shot of May Street construction

Recent drone shot of May Street construction

Swamp sunflower in bloom around the Lakes

Swamp sunflower in bloom around the Lakes

Phase 2A Dredging

Phase 2A dredging, which included the northern half (approximately) of University Lake and College Lake, is complete!

​

Phase 2 Landscaping

Shoreline landscaping is continuing to progress as crews work west to east around the South Lakeshore peninsula. The contractor is now landscaping the third and final segment of new shoreline along South Lakeshore Drive. Maintenance of the completed shoreline areas and islands is ongoing.

Native grasses blooming near May Street and Dalrymple

Native grasses blooming near May Street and Dalrymple

Watering newly seeded turfgrass along S. Lakeshore Drive

Watering newly seeded turfgrass along S. Lakeshore Drive

Phase 2B

Dredging of the southern half of University Lake began in early 2025 and is scheduled for completion this November. The new green space across from the Lod Cook Alumni Center at LSU and the expansion to BREC's Wampold Park are continuing to take shape!

A recent aerial photo showing progress in University Lake

A recent aerial photo showing progress in University Lake

Campus Lake

Dredging continues and is scheduled for completion by the end of November 2026.

​

Mechanical dredging in Campus Lake

Mechanical dredging in Campus Lake

Presentation from

Public Meeting

June 9, 2026

High School students and BR Green planted Cypress trees at University Lake
January 23, 2026

Contracts & Amounts

Contracts
Payments
Task
Sevenson
$54,185,957
Dredging CMAR
Brown Industrial
$11,732,480
May Street Contractor
Sasaki
$4,528,835
Master Designer
Stantec
$2,490,384
Flood Risk Reduction Designer
CSRS/B&D
$2,233,000
Project Advisor
RCI
$3,666,887
Landscape Contractor
Unawarded Landscape
$1,151,057
Landscape Installation & Maintenance
GeoEngineers
$608,042
Geotechnical Engineer
Fenstermaker
$529,317
Surveyor
J&W Contractors
$185,570
Miscellaneous Repairs
Big Gator
$77,500
Brush Clearing
Terracon
$41,070
Consulting Engineer for May Street
Eisner Amper
$25,375
Audit
Taylor Porter
$23,008
Insurance
G&S Aerial
$15,457
Vegetation Management
Louisiana Pond Management
$18,000
Vegetation Management
Bayou Tree Service
$10,100
Vegetation Management
Unawarded Path Construction
$875,850
Shared Use Path Construction
TOTAL
$85,403,162

Funding

Funding
Amount
Capital Outlay
$52,750,000
CBDG
$10,000,000
EBR
$5,350,000
BREC
$5,000,000
LA DOTD
$5,000,000
LSU Foundation
$4,186,300
LSU
$50,000
Interest Earnings to Date
$991,754
TOTAL
$83,328.054
University Lakes 1-10 view
New University May Street Rendering

Current Project

Details

New University Lakes Overview

October 2023

Updates

bottom of page