top of page

The University Lakes Restoration Project team reminds the public that May Street is closed to all traffic between Dalrymple Drive and East Lakeshore Drive.
This applies to vehicles, cyclists, and pedestrians.

Pelicans visit the University Lakes

REIMAGINE THE
LAKES

Exciting changes are coming to

the University Lakes System.

A partnership between LSU and

state and local partners is working

to create a more sustainable lakes system through ambitious environmental restoration that will also add tremendous recreational value for all people of Baton Rouge.

Presentation from Public Meeting

on June 9, 2026

What's Happening at the Lakes?

Phase 1

Dredging in City Park Lake and Lake Erie is complete! Shoreline seeding and landscaping have been installed, and we’re already seeing growth and some bursts of color.


Work on May Street continues. Construction of the May Street bridge will begin in the next few weeks.

Phase 2A

Progress continues in University Lake. Dredging and shoreline landscaping in College Lake was completed in 2025. Dredging in the northern half of University Lake is wrapping up, and landscaping of the newly-creating islands and shorelines is already underway.

Phase 2B

Dredging of the southern half of University Lake began in early 2025 and is scheduled for completion this summer.  The new green space across from the Lod Cook Alumni Center at LSU, as well as the expansion to BREC's Wampold Park, are starting to take shape!

 

Campus Lake

Raking and drainage improvements are complete, and dredging is set to begin this summer.

High School students and BR Green planted Cypress trees at University Lake
January 23, 2026

Dam release at May Street

July 2, 2025

Contracts & Payments
Contracts
Payments
Task
Sevenson
53,753,915
Dredging CMAR
Brown Industrial
11,549,859
May Street Contractor
Sasaki
4,523,010
Master Designer
Stantec
2,420,036
Flood Risk Reduction Designer
CSRS/B&D
2,077,387
Project Manager
RCI
2,771,840
Landscape Contractor
Unawarded Landscape
2,645,838
Landscape
GeoEngineers
613,883
Geotechnical Engineer
Fenstermaker
536,267
Survey
J&W Contractors
123,000
Drainage
Big Gator
77,500
Survey
Taylor Porter
23,008
Legal
Eisner Amper
22,750
Audit
Terracon
12,000
Consulting Engineer May Street
G&S Aerial
6,160
Drone Sprayer for invasive aquatic vegetation

Total $81,161,694

Funding
Funding
Amount
Interest Earnings
986,456
LSU
50,000
LSU Foundation
4,077,500
LA DOTD
5,000,000
BREC
5,000,000
EBR
5,350,000
CBDG
10,000,000
Capital Outlay
50,750,000

Total $81,213,956

University Lakes 1-10 view
Phase 1 overlays

Corps of Engineers Permit

New University May Street Rendering

Current Project

Details

New University Lakes Overview

October 2023

Updates

bottom of page