top of page

The University Lakes Restoration Project team reminds the public that May Street is closed to all traffic between Dalrymple Drive and East Lakeshore Drive.
This applies to vehicles, cyclists, and pedestrians.

Pelicans visit the University Lakes

REIMAGINE THE
LAKES

Exciting changes are coming to

the University Lakes System.

A partnership between LSU and

state and local partners is working

to create a more sustainable lakes system through ambitious environmental restoration that will also add tremendous recreational value for all people of Baton Rouge.

What's Happening at the Lakes?

Phase 1

Work on May Street continues. Pile driving for the May Street bridge has begun!.

The project team conducted a comprehensive site walk on June 22nd, to review progress made on recent landscape installations around University Lake, as well as the maturation of the previously installed shoreline landscaping around City Park Lake and Lake Erie.

 

While the maturation and “filling in” of the plant material installed will take some time, the project team did observe many areas where growth of the native species planted is on track. In other areas, particularly along shoreline edges, growth has been slow due to frequent inundations caused by heavy rain events.  Project landscape architects and contractors are re-evaluating plant selections in those areas.

Landscape maintenance is ongoing to remove weeds, water (as needed), and cut back new growth periodically in the newly landscaped areas.

Phase 2A

Dredging in the northern half of University Lake is wrapping up, and landscaping of the newly created island near West Lakeshore Drive and shorelines at the corner of May Street and Dalrymple is already underway.  New islands and shoreline areas along South Lakeshore Drive and Stanford Avenue will be the next to be landscaped.  Before then, a local contractor will spray the new, invasive vegetation that has already grown on the new shoreline fill.

Phase 2B

Dredging of the southern half of University Lake continues and is scheduled for completion later this summer.  The new green space across from the Lod Cook Alumni Center at LSU, as well as the expansion to BREC's Wampold Park, are continuing to take shape as the geotextile tubes that form the perimeter of green spaces are placed and filled with sediment.

 

Campus Lake

Raking and drainage improvements are complete, and dredging is set to begin in early July.

Presentation from Public Meeting

June 9, 2026

High School students and BR Green planted Cypress trees at University Lake
January 23, 2026

Dam release at May Street

July 2, 2025

Contracts & Amounts
Contracts
Payments
Task
Sevenson
53,753,915
Dredging CMAR
Brown Industrial
11,549,859
May Street Contractor
Sasaki
4,523,010
Master Designer
Stantec
2,420,036
Flood Risk Reduction Designer
CSRS/B&D
2,077,387
Project Manager
RCI
2,771,840
Landscape Contractor
Unawarded Landscape
2,645,838
Landscape
GeoEngineers
613,883
Geotechnical Engineer
Fenstermaker
536,267
Survey
J&W Contractors
123,000
Drainage
Big Gator
77,500
Survey
Taylor Porter
23,008
Legal
Eisner Amper
22,750
Audit
Terracon
12,000
Consulting Engineer May Street
G&S Aerial
6,160
Drone Sprayer for invasive aquatic vegetation
TOTAL
$81,161,694
Funding
Funding
Amount
Capital Outlay
50,750,000
CBDG
10,000,000
EBR
5,350,000
BREC
5,000,000
LA DOTD
5,000,000
LSU Foundation
4,077,500
LSU
50,000
Interest Earnings
986,456
TOTAL
$81,213,956
University Lakes 1-10 view
Phase 1 overlays

Corps of Engineers Permit

New University May Street Rendering

Current Project

Details

New University Lakes Overview

October 2023

Updates

bottom of page