top of page

The University Lakes Restoration Project team reminds the public that May Street is closed to all traffic between Dalrymple Drive and East Lakeshore Drive.
This applies to vehicles, cyclists, and pedestrians.

Pelicans visit the University Lakes

REIMAGINE THE
LAKES

Exciting changes are coming to

the University Lakes System.

A partnership between LSU and

state and local partners is working

to create a more sustainable lakes system through ambitious environmental restoration that will also add tremendous recreational value for all people of Baton Rouge.

What's Happening at the Lakes?

Phase 1

Work on May Street  continues. Pile driving is complete and the new channel connecting University and City Park Lake is being re-excavated.  Next week, the steel girders for the new bridge will start to be installed, and May Street road work east of the channel will continue. 

The project team is developing a new guide to help residents and visitors identify the native plant material that has been planted around the lakes, including a flowering schedule.  Look for this new resource on the website soon. 

 

Landscape maintenance is ongoing to remove weeds and cut back new growth periodically in the newly landscaped areas. 

May Street bridge construction

May Street bridge construction

Phase 2A Dredging

Dredging in the northern half of University Lake is mostly complete.  The contractor will be dredging in a small cove near E. Lakeshore Drive and Christian Street over the next few weeks, as Phase 2A wraps up. 

Phase 2A Landscaping

Landscaping of the newly created island near West Lakeshore Drive is also complete, as are shorelines at the corner of May Street and Dalrymple.  The new islands near South Lakeshore Drive and Stanford Avenue have been cleared and are currently being planted with native material.  The next area to be cleared and landscaped will be the new shoreline along Stanford Avenue, between S. Lakeshore Drive and Milford Wampold Park.   

Phase 2B

Dredging of the southern half of  University Lake  began in early 2025 and is scheduled for completion this September.  The new green space across from the Lod Cook Alumni Center at LSU, as well as the expansion to BREC's Wampold Park, are continuing to take shape! 

Landscaping along Dalrymple

Landscaping along Dalrymple

RCI removing debris

RCI removing debris

Campus Lake

Dredging continues and is progressing nicely! 

Wampold Park Expansion

Wampold Park Expansion

Presentation from

Public Meeting

June 9, 2026

High School students and BR Green planted Cypress trees at University Lake
January 23, 2026

Dam release at May Street

July 2, 2025

Contracts & Amounts
Contracts
Payments
Task
Sevenson
53,753,915
Dredging CMAR
Brown Industrial
11,549,859
May Street Contractor
Sasaki
4,523,010
Master Designer
Stantec
2,420,036
Flood Risk Reduction Designer
CSRS/B&D
2,077,387
Project Manager
RCI
2,771,840
Landscape Contractor
Unawarded Landscape
2,645,838
Landscape
GeoEngineers
613,883
Geotechnical Engineer
Fenstermaker
536,267
Survey
J&W Contractors
123,000
Drainage
Big Gator
77,500
Survey
Taylor Porter
23,008
Legal
Eisner Amper
22,750
Audit
Terracon
12,000
Consulting Engineer May Street
G&S Aerial
6,160
Drone Sprayer for invasive aquatic vegetation
TOTAL
$81,161,694
Funding
Funding
Amount
Capital Outlay
50,750,000
CBDG
10,000,000
EBR
5,350,000
BREC
5,000,000
LA DOTD
5,000,000
LSU Foundation
4,077,500
LSU
50,000
Interest Earnings
986,456
TOTAL
$81,213,956
University Lakes 1-10 view
New University May Street Rendering

Current Project

Details

New University Lakes Overview

October 2023

Updates

bottom of page